Independent Checking of the Financial Arrangement of Tung Chung Line Extension Project

Conduct an independent assessment of the financial arrangement of the Tung Chung Line Extension Project during preliminary and detailed design stages by MTRCL

Project Summary

  • Check the estimated capital and operating costs of the Tung Chung Line Extension Project
  • Check the estimated fare and non-fare revenues of the Tung Chung Line Extension Project
  • Determine the potential contribution from the property development
  • Review the initial capital cost based on the detailed design of Tung Chung Line Extension Project and awarded contract sums of MTRCL’s major construction contracts as submitted by MTRCL

Project Details

Project Owner:
The Government of the HKSAR
Client:
Railway Development Office of Highways Department
Year:
Commencement: 2021 / Planned Completion: TBA
Size:
(Approx)

N/A

Construction Cost:
(Approx)
Construction Cost: TBA